AP · Guide
The AP process in oil and gas
Every dollar a partner sees on a JIB started as a vendor invoice. How that invoice is set up, ticketed, coded and approved decides whether the JIB is right, whether the accrual is right and whether the LOS is right. Here's the process, step by step, and where it usually breaks.
Six steps from vendor to payment
Vendor setup
The vendor is approved and added to the vendor master.
Field ticket
Work is done and documented on location.
Invoice and coding
The invoice arrives and is coded to well, cost center, AFE and account.
Approval
It routes to the people who can confirm the work and the cost.
Payment
Approved invoices are posted and paid on terms.
Cutoff
At month end, what's posted, in approval or not yet received is sorted for close.
1 · Vendor setup
Oil field vendors range from national service companies to one-truck hot-shot operators. Before the first invoice is paid, the vendor should be fully set up:
- Tax form (W-9 for U.S. vendors), so 1099 reporting is right at year end.
- Master service agreement and proof of insurance, usually required before the vendor sets foot on location.
- Rate sheet or price book, so invoice pricing can be checked against what was agreed.
- Payment details verified independently. Bank account changes requested by email are a common fraud attempt. Confirm by phone, using a number you already have on file.
2 · Field tickets
The field ticket is the record that the work happened. It should name the well and location, the date, the crew and equipment, the hours and materials, and carry a signature from the company's field representative. An invoice without a signed ticket behind it is the first thing an auditor, or a partner, will question.
Field tickets also carry the first coding: the field supervisor knows which well the crew was on and whether the work was routine maintenance or part of an AFE.
3 · Invoice receipt and coding
Each invoice line is coded with:
| Code | What it answers | Why it matters downstream |
|---|---|---|
| Well name + cost center | Where the cost belongs | Drives who gets billed on the JIB and which LOS the cost lands on. Lookalike well names are where most mis-codes happen. |
| AFE number | Whether the work was authorized as a project | Partners won't pay AFE work without the AFE. Missing AFE numbers also hide overruns. |
| Cost type | LOE, or an AFE type: Workover, Capital or P&A | Decides the account, the book treatment and how partners are billed. |
| Account | What kind of cost it is (chemicals, rental, labor, IDC, tangible equipment) | Feeds the LOS line items and the capital categories. |
The invoice coding guide and checker covers the rules and checks a batch of coded lines against your well list and open AFEs.
4 · Approval routing
Invoices route to the people who can confirm the work was done and the cost is right: typically the field supervisor first, then the engineer or AFE owner for AFE work, with higher dollar amounts going further up under the company's delegation of authority.
- AFE invoices need the AFE number before they route, so the approver can see the AFE and what's been spent against it.
- Watch for invoices that stall. An invoice sitting in someone's queue past close is still a cost incurred. That's why the approval queue is one of the inputs to the AFE accrual: the accrual is the greater of the field estimate less posted costs, or the unposted invoices in approval.
- Approvers check the work, not just the total. Rates against the price book, hours against the field ticket, and the well against where the crew actually was.
5 · Payment
Approved invoices post to the ledger and pay on the vendor's terms in the next payment run. Posting is what puts the cost on the well: once posted, it's picked up by the JIB for that month and counts as "posted to date" against the AFE.
6 · Month-end cutoff
At cutoff, every cost for the month is in one of three places, and each one is handled differently:
Posted
On the books and on this month's JIB.
- Counts as "invoiced so far" for LOE and "posted to date" for AFEs in the accrual
Received, in approval
Not posted yet, but the invoice is in hand.
- For AFEs, the accrual uses these if they exceed the field estimate less posted
- Don't post them this month and accrue them too
Not received
Work done, no invoice yet.
- Covered by the accrual: the 5-month average and Operations guidance for LOE, the field estimate for AFEs
Where it usually breaks
| Problem | What it causes | Prevention |
|---|---|---|
| Invoice coded to a lookalike well or cost center | Wrong partners billed; two LOS statements wrong | Code to well name + cost center, never name alone; run the coding checker |
| AFE work with no AFE number | Partners hold payment; overruns go unseen | Require the AFE number before AFE invoices route |
| LOE coded to an AFE, or AFE work coded as LOE | Wrong book treatment and partner billing | Check cost type against the AFE type; see capital vs. LOE |
| Duplicate invoice | Partners billed twice | Check vendor + invoice number, and vendor + amount + date |
| Costs charged to a sold or plugged well | Billing partners who no longer own it, or a well with no partners left | Keep well status current in the well master |
| Invoice stuck in approval past close | Cost missing from the month | Review the approval queue at cutoff; it feeds the AFE accrual |
| Equipment moved between wells with no transfer | Cost stays on the wrong well and partners | Report every move to the JIB team, which posts the material transfer |
What JIB needs from AP
- Each invoice coded to the right well name, cost center and AFE.
- The right cost type: LOE, or the AFE's type (Workover, Capital or P&A).
- Clean cutoff: invoices posted by the close date, so accruals cover only what's truly unbilled.
- A visible approval queue, since unposted invoices in approval feed the AFE accrual.
- Equipment moves passed to the JIB team, which prices and posts the material transfer.
Next in the flow: joint interest billing →
The material on this site is general educational information, not legal, accounting or tax advice. Your joint operating agreements, accounting procedures and company policies govern.