JIB · Guide and calculator
Material transfers
Tubing, rods, pumps, tanks and other equipment move between wells and the yard all the time. When they do, the cost has to move too, because the two wells usually have different partners. A material transfer charges the receiving well, credits the sending well, and the JIB bills and credits each well's partners their share. The JIB team prices and posts the transfer; the field reports the move.
Why it matters
Different partners
The well that paid for the equipment and the well now using it rarely share the same owners. Without a transfer, the first well's partners keep paying for equipment that left.
Two sides, one month
The charge and the credit should post in the same month, or one well's LOS and one set of partners' JIBs are off until the other side catches up.
Price by condition
Used material isn't transferred at the price of new. The accounting procedure attached to the JOA sets how it's priced.
Pricing by condition
Accounting procedures commonly price transferred material by its condition, as a percentage of the current price of new material ("Condition A"). One published example is the federal accounting procedure for net profit share leases (30 CFR 1220.015), which uses the scheme below. COPAS model forms differ by version, so check the accounting procedure attached to your JOA; the calculator lets you change the percentages.
| Condition | Meaning | Priced at (example procedure) |
|---|---|---|
| Condition A | New material | Current price of new material |
| Condition B | Good used: sound, serviceable and reusable without reconditioning | 75% of the Condition A price. In that procedure, material moving out that was originally charged in as Condition B moves at 65%. |
| Condition C | Needs reconditioning before it can be used for its original purpose | 50% of the Condition A price |
| Condition D | Usable, but worth less than A, B or C | An agreed value, reflecting the service it will give |
In that procedure, the receiving party bears the cost of reconditioning Condition B, C or D material.
Transfer calculator
Material
From (sending)
To (receiving)
Entry (100% of the transfer)
| Line | Debit | Credit |
|---|
Who bears it
| Party | Charge (credit) |
|---|
Reviewing transfer entries
- Both sides, same month. The receiving charge and the sending credit post together.
- Right wells on both sides. Well name and cost center on the sending and receiving lines, so the right partners are billed and credited.
- Condition documented. The transfer ticket shows who classified the condition, and the pricing follows the accounting procedure.
- Price support. Condition A pricing comes from a current supplier price or price list, not the original invoice from years ago.
- Receiving side coded correctly. LOE, or the receiving well's AFE and type when the material goes into AFE work.
- No transfer, no move. Equipment that shows up on a well without a transfer ticket leaves its cost behind on the wrong partners. Ask the field to report every move to the JIB team.
Transfers between wells are one of the monthly entries reviewed in the JIB close. See the JIB month-end close checklist.